Construction Bidders: US$17 Million to Construct Health Buildings Is Stalled because of Foreign Advisors - Tuesday 3.2.2009

Posted on 3 March 2009

The Mirror, Vol. 13, No. 602

“Phnom Penh: A US$17 million loan from the World Bank to build referral hospitals at provinces as well as many health centers and posts has been stalled for two years, because of a lack of management competency of foreign advisors from LBG [unclear what LBG stands for in the original - maybe the quantity surveyor company LBG-NGT Corporation from Tuas/Singapore – but maybe not]. This was stated by construction bidders who attended biddings to implement this project.

“Construction bidders criticized that for two years, there has been no construction, but there were one or two biddings. Because of this slowness, the construction of up to 10 referral hospitals and many health centers and posts in most provinces, worth more than US$10 million, has been stalled until now.

“The same source added that though recruitment for the construction project was transferred to IPA [unclear what IPA stands for in the original – maybe the recruitment company Independence Procurement Agency – but maybe not] by the Ministry of Economy and Finance recently, this project still faces the possibility of failure. It is said that the trouble originates from the LBG advisors .

“The source blamed that the technical advisors of LBG are incompetent to do the managing, and furthermore, in the plans, there are no calculations based on standard formulas and on proper construction standards. This is a major obstacle for the construction bidders, and even though many companies had protested against the mistakes of the LBG technical advisors, there was no action taken by the Healthcare Services Specification Project of the Ministry of Health.

“According to the bidders, the project was put for bidding again for a second time at the end of 2008, but still there were not many bidders attending. There will be a third bidding, and this may be continue forever.

“Bidders know well that even if one or two more biddings are held, there still will be no bidders.

“Moreover, the rushed delivering of contracts for two projects, the Kampot and the Stung Treng referral hospitals, worth more than US$2 million, in mid February 2009 by IPA, leads to a loss of tens of thousands of dollars, because the price of the bidding for this project was 60% to 80% higher compared to the formerly calculated price.

“The source went on to say that the construction processes at most places have been stalled for years, which makes the expenses for technical advisors to increase by more than 20%, which is most highly problematic. Bidders criticized this and also requested that leaders of the Ministry of Health should check the contracts between the ministry and LBG advisors urgently. At the same time, they have to recheck the management system at the secretariat supporting the heath sector.

“Bidders still remember Samdech Dekchor Hun Sen’s former words, saying that substantial expenses for foreign advisor services were right. Bidders emphasize that this is not acceptable. Everyone knows that better health services in rural areas are desperately needed by citizens almost everywhere, and also in this priority sector of the Royal Government, which is to be strengthened. Thus, the above source calls on the Ministry of Health to thoroughly check and take action against any negative points, or any individual who wastes a lot of national resources, because all money to support the health sector comes from all Cambodian citizens who will have to repay the loan to the World Bank in the future.

“Regarding what is mentioned above, Rasmei Kampuchea tried to contact the secretariat of the Ministry of Health, and LBG, for explanations, but could not reach them.”

Rasmei Kampuchea, Vol.17, #4835, 3.3.2009